The time frame goes something like this
Setting out and foundation prep 1 day
Concrete footing and base 1 day + 2 days to dry
Mortar in blockwork 1 day + 2 days to dry
Concrete fill blockwork 1 day and minimum 3 days to dry before oven can be installed on top
The above will take approx. 2.5 weeks BUT is dependent on weather and other events happening in school eg production
My aim would be to have the base ready for the oven at the end of week 9 for installation in week 10
Alastair