The time frame goes something like this

Setting out and foundation prep 1 day

Concrete footing and base 1 day + 2 days to dry

Mortar in blockwork 1 day + 2 days to dry

Concrete fill blockwork 1 day and minimum 3 days to dry before oven can be installed on top

The above will take approx. 2.5 weeks BUT is dependent on weather and other events happening in school eg production

My aim would be to have the base ready for the oven at the end of week 9 for installation in week 10

Alastair